Hi,
we are trying to figure out how to calculate the Irrigation cost in the Schematic design. For instance, we have a Turf Rotor 7.6-13.7 m area with the assigned cost of 0.4 eur/m2. In the Irrigation schedule, the total turf rotor area is 8,077 m2, cost 0.4 eur, and total cost 34,775 eur. The math is not clear to us. Shouldn't the total cost be 8,077 x 0.4 = 3,230.8 eur?
Similar happens with other types of irrigation areas.
Thank you!
Best regards,
Slavica